Lance-MODIS Terra 2017-01-19 16:05-17:15 C5 PGE01 errors and 14:40,17:50 LST not produced during DMU #99
Platform | Terra |
---|---|
Instrument | MODIS |
Source | lance-modis |
Issue | news |
Last Updated | 2016-10-21 21:00:00 |
Start | 2017-01-19 14:40:00 |
End | 2017-01-19 17:55:00 |
Description |
2016-10-21T15:20:00Z Lance-MODIS C5 processing systems nrt1 and nrt2 failed PGE01 for fourteen granules between 2017-01-19 16:05 and 17:15 during the Terra DMU #99 maneuver. No C5 granules were produced during that interval other than MOD00F. The C6 instances nrt3 and nrt4 processed these granules without error. We encourage users to favor C6 over C5 as C5 production will cease after 2017-03-31. Some Land products including LST at 2017-01-19 14:40 and 17:50 were not produced in both C5 and C6 because the granule was determined by PGE138 to be too distorted by the maneuver. |